2018 Reconnecting New Zealand

BUY NOW ON WOPA+

New Zealand – On 14 November 2016, a magnitude-7.8 earthquake struck 15km north-east of Culverden, North Canterbury. The event’s impact on road and rail infrastructure was instant and devastating. The South Island itself moved, thousands of landslides came down, and land rose and slumped along the eastern coast. This issue illustrates the determination that literally moved mountains to reconnect communities and New Zealand.

It took one year, one month, and one day to reopen State Highway 1 after the 7.8 magnitude Kaik?ura Earthquake on 14 November 2016. Freight trains had returned to the railway just 10 months after tracks had been thrown into the sea. In all, 1,700 people worked more than 2 million hours to move mountains and reconnect the communities isolated by the quake.

It was an extraordinary response to an extraordinary seismic event: 21 faults had ruptured, generating the strongest ground shaking ever recorded in New Zealand. The South Island itself moved, thousands of landslides came down, land rose and slumped along the eastern coast. Transport infrastructure was devastated, with coastal and rural communities isolated overnight. The instant disruption to tourism, freight and primary industries was felt nationwide.

The North Canterbury Transport Infrastructure Recovery alliance was set up to restore the network, and keep traffic moving on alternate routes. This partnership between the NZ Transport Agency and KiwiRail was new territory, as was the collaboration of Downer New Zealand, Fulton Hogan, HEB Construction and Higgins on such scale. With work sites spread over a large geographical area stretching from North Canterbury to Marlborough – some very remote – the recovery effort sought to merge the knowledge of local contractors with resources from all over New Zealand. The team would grow to 1,700 people from over 100 organisations over 2017.

It was a national effort, with supplies travelling the length of the country. Bridge beams and seawall blocks were manufactured on both Islands and brought to site by road and rail. It wasn’t until early Spring that supplies could be moved between sites north and south of ?hau Point, where the largest landslide had fallen. Repairs on the Main North Line represented the largest rail construction effort since World War II, with 220 work sites along 190km of track. Kaik?ura harbour was returned to the community exactly one year after the quake, and the NZ Transport Agency committed to reopening SH1 on 15 December. Due to rain, the team was pushed to the wire. In the hours before the gates swung open, the updraft from helicopters was used to dry the road so chip seal could be laid in order to make good on the promise to open the road.

The isolated communities were finally reconnected. Though the landscape remains fragile and there are still significant improvement works to do, the rebuild is a testament to what can be achieved when people work together with a clear vision and determination.

Individual Stamps 

$1.00 – Shape of the Future

At Irongate Stream north of Kaik?ura, SH1 was moved seaward and away from a large landslide. A new seven-span bridge sweeps from a bluff at the southern end, landing on its new alignment atop a seawall. The old road will eventually be used as a rockfall catchment area. More than 100 bridges needed to be repaired or replaced after the earthquake. Taking about three months to complete the superstructure, the 144m bridge at Irongate was the fastest build of its kind in New Zealand history.

$1.00 – Taming the cliffs

Geotech teams and abseilers were an integral part of the transport recovery. In the early months they acted as ‘spotters’ that warned crews below if a landslide started to move. Working from hilltop base camps, some only accessible only by helicopter, they helped dislodge boulders and remove vegetation from the slips. They also installed geomesh and rockfall fences on the slopes. One very special job was helping the Department of Conservation to retrieve seeds of the rare ?hau rock daisy. The plant grows only on the bluffs of ?hau Point north of Kaik?ura and was almost wiped out by a landslide.

$2.00 – Moving mountains

Some landslides generated 10,000 truckloads of material, always peppered with large boulders. All of the rubble needed to be transported through narrow work sites along the coast, often relayed to temporary stockpiles which could grow to two storeys high. Keeping that fleet of dump trucks moving while bridges, culverts, roads and the railway were being rebuilt was a logistics exercise of epic proportion. This particular landslide, which came down just south of Peketa, severely damaged rail Tunnel 13.

$2.20 – A hard road

Until access could be established around the largest and most complex slip at ?hau Point, it was the ‘end of the road’ for crews working north and south. These were isolated work sites, making it difficult to get materials in. Seawall blocks, each weighing five tonnes, arrived six at a time – that’s all that could fit on the back of a truck. The seawall teams worked towards each other from each side of the Point, progressing metre-by-metre as the slip above them was cleared and secured with geomesh, making it safe to work below.

$2.70 – Engines that could

Bringing KiwiRail’s specialised work trains into the coastal corridor was a priority during the rebuild. They were needed to carry out track repairs and to transport construction materials. Sometimes temporary structures were built so the work trains could advance towards Kaik?ura, with permanent repairs occurring later. Bridge 131 at Wharenui north of Kaik?ura, where readily available steel spans were pressed into use, was an example of the ‘fast if sometimes ugly’ approach that got the railway open.

$3.30 – A special delivery

The first freight train to travel the Main North Line after the earthquake, pictured here south of Öaro, made the journey from Picton to Christchurch on 15 September 2017. Hundreds of people turned out to meet the train along the way. The return of freight trains, even in a limited capacity, removed about 2000 trucks off the alpine route through Lewis Pass. Five weeks earlier, the railway had been fully connected with a ‘final weld’ at a ceremony at Half Moon Bay north of Kaik?ura.

Presentation Pack

Find out more about the economic and social impacts around the importance of why SH1 and the rail corridor needed to be reopened as soon as possible. The presentation pack makes the perfect collectable, or a great gift for an engineering enthusiast.

  • 02.05.2018
  • Saint Andrew Matautia, New Zealand Post, Wellington, New Zealand
  • Southern Colour Print Ltd, Dunedin, New Zealand
  • Four process colours
  • 30mm x 50mm (horizontal)
  • $1.00 x2, $2.00, $2.20, $2.70, $3.30